Autoroute 4 K 02

Office building Be-One

Built entirely of timber and with no concrete above the foundations, Be-One is a particularly ambitious office building.
  • Architect: Sharp Architectures with Bureau Bouwtechniek

  • Partners: Beneens Bouw en Interieur (general contractor)

  • Client: United Consulting

  • Surface: 15.000 m2

  • Timing: 2026 -

  • Status: In execution

  • Advisors: WOW Engineering (stability), Gebotec (techniques), D2S (acoustics)

XPAND05 V Ray Cam007 10

Where sustainability and design come together

Be-One is one of Belgium’s first fully integrated ESG office buildings. Apart from the foundations, there is no concrete in the building. Instead, it contains 3,500 m³ of timber. More than 1,000 solar panels are integrated into the façade and, together with the geothermal system, ensure complete energy neutrality.

An independent Life Cycle Analysis confirms Be-One’s exceptional environmental impact. Whilst an average European office building emits 528 kg of CO₂ equivalent per m², Be-One sequesters a net total of 235 kg of CO₂ equivalent per m².

The choice of timber saves 3.9 million kg of CO₂ compared to a similar concrete building – equivalent to driving 680 times round the Earth.

Screenshot 2026 05 05 at 14 56 44

Continuum

The building is based on a biophilic vision in which nature, light and well-being take centre stage. There are no traditional storeys, but rather a gentle 600-metre slope that connects the entire space as a single whole.

A central atrium brings daylight deep into the building and forms the architectural heart of Be-One. The indoors and outdoors gradually merge, and nature is given a permanent place throughout the entire building.

The result is a working environment that feels calmer, more human and more connected.

XPAND05 V Ray Cam002 009

Figures

• Over 6,000 m² of workspace
• 3,500 m³ of timber (CLT)
• Over 1,000 integrated solar panels
• Geothermal system for heating and cooling
• A 30-metre-high landmark featuring an atrium
• A 600-metre-long ramp running through the building
• Over 240 parking spaces and 60 charging points
• Net CO₂ storage of 235 kg CO₂-eq/m² (compared to +528 kg emissions for an average European office)

As the architect’s technical partner, we apply our structural engineering expertise to ensure a smooth transition from design to construction. (development of construction details and the specifications)

We take the pressure off the architect by monitoring the realisation of design ambitions during construction and resolving construction-related issues from a structural engineering perspective.

We contribute our structural engineering expertise to the discussions between the architect and the contractor to jointly arrive at feasible and widely supported construction principles.

Our project architects

From Team Architecture (private sector Antwerp, Limburg, Flemish Brabant and Brussels) (2)

Steven 569 A0822 Gemiddeld

arch. Steven Wauters

Project architect
E-mail |
FREDERIQUE 9 6 23 569 A8845 Gemiddeld

ir. arch. Fréderique Vermeyen

Project architect
E-mail |
TAGS: Executive architect