VME Héliport 1 engaged us for a comprehensive feasibility study on the necessary maintenance works on the facades and balconies of the apartment building on Schipperijkaai in Brussels.
  • Client: VME Héliport 1

  • Timing: 2024

  • Status: Executed

  • Advisors: Sanacon (concrete study)

This 1973 building suffers from several structural and energy challenges that call for a short- and long-term strategic renovation approach.

DSC06511 Groot

Main findings

Numerous defects were identified during site inspections and analysis of existing documents.

  • Damage to the concrete terraces: carbonation and chloride contamination of the structural concrete.
  • Safety hazards due to corroded and damaged balustrades.
  • Problems with waterproofing on the terraces.
  • Damage to the natural stone façade panels.

The building in its current state does not meet the energy standards set out in the Brussels RENOLUTION strategy for 2050.

DSC06295 Groot

Plan of action

We investigated the causes of the identified damage and subcontracted a concrete survey to map the evolution of chloride contamination and carbonisation of the concrete.

We drew up a strategy focusing on necessary short-term conservation works and medium- and long-term energetic and structural improvements.

  • Short-term: Replacement of the concrete that is too affected by chlorides, renewal of waterproofing, repair of local concrete damage and replacement of balustrades and terrace partitions.
  • Medium-term: Guidelines for the private replacement of joinery, which would optimise long-term communal renovation.
  • Long term: Three different scenarios for facade renovations with possible insulation measures and modifications to terraces.

Safety and sustainability

The proposed measures focus not only on structural improvements, but also on increasing the safety and sustainability of the building. For instance, the current standards for parapets and fire safety also serve as a basis for the analysis.

project team

From Team Renovation, Restoration & Maintenance (2)

BB Arno oct 2014

ir. arch. Arno Van Hulle

Project architect
Maintenance consultant
E-mail |
Gust

ir. arch. Gust Mannaerts

Project architect
E-mail |

Are you also in need of a feasibility study?

Do not hesitate to engage us, we will be happy to work with you to see which plan of action best suits your capabilities.

TAGS: Feasibility study